When Should You Stress a Cable Slab?

Featured Article

The question as to when the proper time to apply the stressing force to the post tensioned cable in this type of reinforced foundation is of considerable interest. If you apply the stressing load too soon you have the danger of pulling cable anchorages out of the green concrete. If you wait too long there is a problem of excessive loads being applied to the foundation, due to the super structure framing proceeding and, probably most significant, the increase in number and width of shrinkage cracks which could occur in the un-reinforced foundation.

Post tensioned slabs should be stressed when the concrete strength designated by the engineer’s plan is reached.  The practice of MLAW has been to apply stress when the concrete reaches 2000 psi. Good quality concrete should reach 2000 psi in approximately 4 days under normal curing conditions, and certainly within 7 days. If 2000 psi is not reached within 7 days, the concrete will probably not reach 3000 psi in 28 days.

Loadings should not be placed on the slab beyond the basic framing and possibly composition shingle roofing. Certainly no sheetrock or any other heavy loads should be applied to the structure before stressing the cables. Remember, the foundation slab is in a totally unreinforced condition prior to stressing.  The best time to apply the stressing would be between 4 and 7 days and certainly before significant loads are applied to the foundation. The strength of the concrete at the time of the stressing should be verified by some type of indirect concrete testing procedure such as an impact hammer or other technique.

Kirby T. Meyer, P.E.
MLAW Consultants & Engineers
Originally published in MLAW Newletter, January 2006

Explore

MLAW Engineers, Structural Engineering, Austin, San Antonio, Houston, Dallas, Temple, Waco, Killeen, Bryan, College Station

Balconies, Stairs and Landings

By Staff Editor | March 17, 2022

Of the various types of balconies, the overhanging or cantilever types are potentially the most dangerous. Balconies can be found on single family dwellings, but most frequently are found in condominiums or apartments. A balcony can totally collapse if it becomes structurally unsound. Many deaths and serious injuries have resulted from collapse.  Balcony live loadings…

Read More
MLAW Engineers, Structural Engineering, Austin, San Antonio, Houston, Dallas, Temple, Waco, Killeen, Bryan, College Station

Steel Framing for Residences

By Staff Editor | March 17, 2022

Steel structural framing has been used for many years in commercial construction. It is only used rarely for residential construction. The main reason appears to be that “it has always been done that way”. Another reason is probably that homebuilders do not have access to subcontractors who are familiar with utilizing steel as a construction…

Read More
Posted in

Staff Editor

MLAW Engineers is recognized as one of the most respected structural engineering firms in Texas. Over 54 years of superior engineering by MLAW Engineers can be seen in over 400,000 completed projects nationwide.

1 Comments

  1. Tino Ambriz on June 13, 2023 at 5:29 pm

    Good afternoon on a 9 inch post tension elevated slab after our stress test is done how long before you take drive any equipment on to continue going up with or put any weight on it

Leave a Comment